Tupper Industrial Developers Limited, Point Tupper, Nova Scotia, Canada- office and warehouse space.

Architectural Style Single story industrial warehouse with two-story office section
Year Built 1980
Building Base Area 1,997.8 m2
   
Brief Specifications  
   
Exterior  
Foundation Poured Concrete
Walls Steel insulated sandwich panels
Frame Steel
Roof Tar and gravel finish on steel Q-decking on open web steel joists
Insulation – Walls Fibreglass in walls
Insulation – Roof Rigid insulation
Windows Double glazed windows in aluminum frames
Doors Double entrance doors: One set glazed in aluminum frame
  Individual doors: Eight metal faced in metal frames
  Vehicular doors: Nine metal panel overhead type doors
Chimney None
Fire Escape/Exterior Staircases None
Downspouts and Guttering None
Porches and Steps None
Structural Repair Good
Paintwork Good
   
Interior  
Basement None
   
Ground Floor  
Ground Floor – Washrooms and Locker Rooms  
Floor Quarry tile and vinyl asbestos tile
Walls (finish) Washrooms- Ceramic tile
  Locker rooms- Painted concrete block
Ceilings (finish) Exposed open web joists and decking
Doors and Trim Solid core doors with metal trim
Clear Height +/-2.5 m
Ground Floor – Offices in the Workshop Sections  
Floor Poured concrete and vinyl asbestos tile
Walls (finish) Painted concrete block and painted gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile and painted gyproc
Doors and Trim Solid core doors with metal trim
Clear Height 2.4 m
Ground Floor – Finished Space (Remainder)  
Floor Vinyl asbestos tile
Walls (finish) Painted concrete block and painted gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +/- 2.5 m
Ground Floor – Woodworking Shop  
Floor Poured concrete
Walls (finish) Painted concrete block
Ceilings (finish) Painted gyproc
Doors and Trim Solid core doors with metal trim
Clear Height +/- 2.5 m
Ground Floor – Unfinished Space (Remainder)  
Floor Poured concrete
Walls (finish) Concrete block
Ceilings (finish) Exposed open web joists
Doors and Trim Solid core doors with metal trim
Clear Height 6.93 m
   
SecondFloor  
Second Floor – Washrooms  
Floor Quarry tile
Walls (finish) Ceramic tile
Ceilings (finish) Suspend 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +/- 2.4 m
Second Floor – Electrical and Mechanical Rooms  
Floor Vinyl asbestos tile
Walls (finish) Painted concrete block
Ceilings (finish) Exposed open web joists
Doors and Trim Solid core doors with metal trim
Clear Height +/- 2.5 m
Second Floor – Remainder  
Floor Carpet and vinyl asbestos tile
Walls (finish) Painted gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +/- 2.4 m
   
Plumbing  
Fixtures and Location Ground floor:
  1 x 7 piece washroom with shower room (4 shower heads)
  1 x 6 piece washroom with shower room (4 shower heads)
  4 stainless steel sinks in Kitchen
  1 Drinking fountain in corridor
  Second Floor:
  1 x 5 piece washroom
  1 x 4 piece washroom
Equipment Two x 60 gallon John Wood electric hot water heaters
   
Heating  
Type of Furnace Steam heat supplied from central heat exchanger unit located on site
Type of Radiation Finished space: Baseboard heaters
  Pipe and Fab shop and locker rooms: Ducted hot air
  Remainder: Overhead space heaters
Zoned Heating All workshops and office areas have separate zones
Supplementary Heating Locker rooms: Electric baseboard heater
  Garage: Overhead electric heater with ducted air radiation

   
Air-conditioning  
Type of Air-conditioner Cafeteria: Air circulation system
Type of Radiation Ceiling mounted vents
Supplementary Ventilation Pipe and Fab shop: Four 'smog hog' industrial air cleaning units
  Iron workers shop: One 'Smog Hog' industrial air cleaning unit
   
Electrical  
Service Entrance Three phase, (7) 600V, 225 Amps
Fixtures Finished space: Recessed fluorescent lighting
  Unfinished space:
  Woodworking shop fluorescent
  Remainder incandescent
   
Sprinkler System  
Type Wet charged system throughout
   
Fire Protection  
Sensors Smoke sensors throughout
Pull Stations Throughout
Fire Alarm Panel 'Edwards of Canada'
  Located in Ground floor entrance
Emergency Lighting 'Rycroft', 'Teledyne' (and other) battery units throughout
   
Elevators None
   
Fixed Equipment  
Type One 'Munck' gantry
Size (Capacity) Ten ton
Location Pipe and Fab shop