Site Specifications for Warehouse and Office Building two

Table of Contents
Exterior
Interior
- Ground floor
- Second floor
Plumbing
Heating
Airconditioning
Electrical
Sprinkler System
Fire Protection

Tupper Industrial Developers Limited, Point Tupper, Nova Scotia, Canada- office and warehouse space.

Architectural Style Single story industrial warehouse with two-story office section
Year Built Main structure: 1968
  Emergency generator building: 1980
Building Base Area Main structure 3,081.2 m2. (Excludes card rack building, built in 1981)
  Emergency generator building 62.6 m2
   
Exterior  
Foundation Poured Concrete
Walls Storage and workshop area: Aluminum V-beam aiding
  Office section: Facing brick with aluminum V-beam facade
Frame Steel
Roof Main structure: Tar and gravel finish on steel Q-decking on open web and steel joists
  Emergency generator building: Steel Q-decking
Insulation – Walls 38 mm Polystyrene
Insulation – Roof 25 mm Rigid insulation
Windows Single glazed windows in metal frames
Doors Double entrance doors:
  Two sets glazed in aluminum frame
  Two sets metal faced in metal frames
  Individual doors: Four metal faced and glazed in metal frames
  Vehicular doors: Four metal roller shutter type
Chimney One steel chimney
Fire Escape/Exterior Staircases Metal staircase up to roof
Downspouts and Guttering Main structure: None
  Emergency generator Building: metal gutter and downspout
Porches and Steps None
Structural Repair Good
Paintwork Good
   
Interior  
Basement None
   
Ground Floor  
Ground Floor – Entrance, Corridor (Part)  
Floor Quarry tile
Walls (finish) Painted concrete block, facing brick and plywood
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core/glazed doors with metal trim
Clear Height +- 2.4 m
Ground Floor – Washrooms  
Floor Quarry tile
Walls (finish) Ceramic tile and painted concrete block
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +- 2.4 m
Ground Floor – Locker room  
Floor Quarry tile
Walls (finish) Painted concrete block
Ceilings (finish) Exposed open web joists and steel decking
Doors and Trim Solid core doors with metal trim
Clear Height 3.7 m
Ground Floor – Safety Equipment Room, Instrumentation Shop #2 and offices in the workshop  
Floor Poured concrete
Walls (finish) Painted concrete block and painted gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +-2.4 m
Ground Floor – Office Section (Remainder)  
Floor Vinyl asbestos tile
Walls (finish) Painted concrete block and painted and vinyl covered gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core/glazed doors with metal trim
Clear Height 2.4 m
Ground Floor – Storage and Workshop Section (Remainder)  
Floor poured concrete
Walls (finish) Painted concrete block
Ceilings (finish) Exposed steel joists and steel Q-decking
Doors and Trim Metal faced doors with metal trim
Clear Height Below mezzanine 3.7 m
  Remainder 8.4m
   
SecondFloor  
Second Floor – Washrooms  
Floor Slate
Walls (finish) Ceramic tile and vinyl
Ceilings (finish) Suspend 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +- 2.4 m
Second Floor – Lab  
Floor Vinyl and ceramic tile
Walls (finish) Painted concrete block and painted gyproc
Ceilings (finish) Suspend 'T' bar with acoustic tile
Doors and Trim Hollow core doors with metal trim
Clear Height +- 2.4 m
Second Floor – Remainder  
Floor Carpet and vinyl asbestos tile
Walls (finish) Painted concrete block and vinyl covered gyproc
Ceilings (finish) Suspended 'T' bar with acoustic tile
Doors and Trim Solid core doors with metal trim
Clear Height +- 2.4 m
   
Plumbing  
Fixtures and Location Ground floor
  1 x 9 piece washrooms
  1 x 3 piece washrooms
  2 sinks in Medical Centre
  1 sink in Safety Equipment room
  Second Floor
  1 x 8 piece washroom
  1 x 6 piece washroom
  Lab
  "Emergency Eye Wash unit
  Several chemical waste sinks
Heating  
Type of Furnace Canadian Blower Forge Co. warm air unit distributes heat through building
  Steam heat Supplied from central heat exchanger unit located on site
Type of Radiation Ducted hot air through ceiling mounted vents
Zoned Heating Storage/Workshops and Office section have separate zones
Supplementary Heating One hot water space heater located on ground floor near computer room
  Electric baseboard heaters in some ground floor offices
   
Air-conditioning  
Type of Air-conditioner Air circulation system throughout the office sections
Type of Radiation Ceiling mounted vents
Supplementary Ventilation Payroll Section: Two wall mounted unit air-conditioners
  Computer room: Two wall mounted unit air-conditioners
  Lab: One wall mounted air chiller unit
   
Electrical  
Service Entrance 600V, 400 Amps
Fixtures Office sections, Lab and Workshop below Mezzanine: fluorescent lighting
  Remainder of Storage/Workshop Section: Mercury vapour lighting
Equipment P.A. system throughout the building
Service Entrance 600V, 400 Amps
Fixtures Office sections, Lab and Workshop below Mezzanine: fluorescent lighting
  Remainder of Storage/Workshop Section: Mercury vapour lighting
Equipment P.A. system throughout the building
   
Sprinkler System  
Type Wet charged system throughout
   
Fire Protection  
Sensors Smoke sensors in office sections
Pull Stations Throughout
Fire Alarm Panel 'Edwards of Canada'
  Located in Central Control Room
Emergency Lighting 'Teledyne' (and other) battery units throughout
Other Computer room and Central Control Room: Ceiling mounted Halon units
Elevators None
   

Printabe version of building using Adobe Acrobat (pdf):

The printabe versions of the building perspectives have been created using Adobe Acrobat and requires
the Adobe Acrobat Reader which can be dowloaded here.